PASSAVANT Energy & Environment received Taking-Over Certificate for WWTP Gabal El Asfar
10.08.2018 01:23
(comments: 0)
PASSAVANT Energy & Environment GmbH is pleased to announce in 2018 the completion of WWTP Gabal El Asfar the biggest Wastewater Treatment Plant in Africa. The project was successfully executed in a Joint Venture together with Acciona Agua and Hussien Atieh & Sons Co.
The project includes the design, construction and commissioning of the WWTP as well as its operation and maintenance contract. The plant has a treatment capacity of 500,000 cubic meters per day and caters to the needs of the eastern part of the Egyptian capital, equivalent to a population of about 2 million people.
GENERAL INFORMATION
- Project: Gabal El Asfar WWTP
- Client: Construction Authority for Potable Water and Wastewater (CAPW)
- Location: Cairo, Egypt
- Flow Capacity: 500,000 m³/d, Population: 2,000,000 P.E.
- Commissioning: July 2018
- Taking Over: August 2018
- Operation & Maintenance: 24 Month